Most of the demolition is complete and new construction areas are evident. The second story with 2 bedrooms and 2 baths has been rebuilt and Loewen windows are being installed. The entry wall with bell tower has been raised 18″and … Continue reading
Posted in Restoration
Carport Complete
This carport structure is complete other than final grading. Three center bays are enclosed with corrugated steel panels. The bays on either end are open. Each of the sliding corrugated doors across the front slide either way for access. The … Continue reading
Posted in Special Projects
ENTRAN Hydronic heating
Entran hydronic heat tubing was used in many houses in the late eighties and early nineties. It was manufactured by Goodyear and became the subject around 2001 of a national class action suit. It was determined that the tubing used … Continue reading
Posted in Heating and Cooling
Curved Steel Joists
The steel joists have been installed with the detailing to take a few more days. After a primer is applied the IMETCO roof will be installed. Final ceiling finish calls for a smooth trowel cementitious plaster. Due to wind load … Continue reading